top of page
  • Twitter - Black Circle
  • Google+ Social Icon
  • LinkedIn Social Icon

Understanding Contract Assets and Liabilities in Construction Accounting

  • Zane Bodnar
  • 6 days ago
  • 3 min read

In the construction world, revenue isn’t earned all at once — it’s built over time, just like the projects themselves. Because of this, contractors often use the percentage-of-completion method (POC) to recognize revenue.


But along with that method comes two key balance sheet accounts that can confuse even experienced contractors: contract assets and contract liabilities.


Let’s break down what they are, how they’re calculated, and why they matter.


What Are Contract Assets and Contract Liabilities?


Under ASC 606: Revenue from Contracts with Customers, construction companies must measure progress and recognize revenue as work is performed — not necessarily when they bill or collect cash.

This timing difference between work performed, amounts billed, and cash received creates either:

  • A Contract Asset → when work performed (revenue recognized) exceeds the amount billed.

  • A Contract Liability → when billing exceeds the amount of work performed (revenue recognized).


In simple terms:

  • Contract Asset = “We’ve earned it, but haven’t billed it yet.”

  • Contract Liability = “We’ve billed it, but haven’t earned it yet.”


The Foundation: Cost-to-Cost Method


Most construction contractors measure project progress using the cost-to-cost method, which compares costs incurred to date against total estimated costs for the job.


Formula:

Percentage Complete=Cost Incurred to DateTotal Estimated Cost\text{Percentage Complete} = \frac{\text{Cost Incurred to Date}}{\text{Total Estimated Cost}}Percentage Complete=Total Estimated CostCost Incurred to Date​


That percentage is then applied to the total contract revenue to determine how much revenue should be recognized to date.


Revenue Recognized to Date=Percentage Complete×Total Contract Price\text{Revenue Recognized to Date} = \text{Percentage Complete} \times \text{Total Contract Price}Revenue Recognized to Date=Percentage Complete×Total Contract Price


Once you’ve determined how much revenue should be recognized, you can compare it to the amounts billed to calculate the contract asset or liability.


Step-by-Step Example

Let’s walk through an example.

Project Overview

Item

Amount

Contract Price

$1,000,000

Estimated Total Cost

$800,000

Cost Incurred to Date

$400,000

Billed to Date

$350,000

Cash Collected

$300,000

Step 1: Calculate Percentage Complete

400,000/800,000=50%400,000 / 800,000 = 50\%400,000/800,000=50%


Step 2: Determine Revenue Earned to Date

1,000,000×50%=500,0001,000,000 \times 50\% = 500,0001,000,000×50%=500,000


Step 3: Compare to Billed Amounts

Description

Calculation

Result

Revenue Recognized to Date

$500,000


Less: Amount Billed

($350,000)


Contract Asset

$150,000


In this case, the contractor has performed $500,000 worth of work but has only billed $350,000.The $150,000 difference is recorded as a Contract Asset (Unbilled Revenue) on the balance sheet.


Step 4: Reverse Example — Contract Liability

If the contractor had billed $600,000 to date instead of $350,000:

Description

Calculation

Result

Revenue Recognized to Date

$500,000


Less: Amount Billed

($600,000)


Contract Liability

$100,000


Why It Matters


Accurate reporting of contract assets and liabilities provides:

  • Better cash flow forecasting — knowing how much work has been earned vs. billed

  • Clearer financial performance — avoids overstating or understating revenue

  • Compliance with ASC 606 — required for GAAP financials and bonding

  • Improved communication with sureties and banks — lenders analyze underbillings and overbillings closely


Common Mistakes Contractors Make


  1. Not updating total estimated costs — inaccurate cost forecasts distort completion percentage.

  2. Confusing billings with revenue — revenue is earned based on work performed, not invoices sent.

  3. Ignoring change orders — pending approvals can skew revenue recognition.

  4. Failing to reconcile WIP schedules — discrepancies between WIP and financial statements cause audit issues.


Pro Tip: Use a WIP Schedule


A Work-In-Progress (WIP) schedule is the backbone of contract asset/liability calculations. It summarizes:

  • Contract price

  • Costs to date

  • Estimated costs to complete

  • Billings to date

  • Revenue earned

  • Over/under billings


Updating this schedule monthly helps contractors track profitability and prevent unpleasant surprises at year-end.


Conclusion:

Contract assets and liabilities are essential for accurately portraying a construction company’s financial position. They tell the story of how much work has been performed versus how much has been billed — and, ultimately, how the company is managing cash and performance.


By mastering the cost-to-cost method, maintaining accurate WIP schedules, and understanding the flow of revenue recognition, contractors can stay compliant, confident, and financially strong.

 
 
 

Comments


RECENT POST
  • Grey Google+ Icon
  • Grey LinkedIn Icon

© 2017 Zane Bodnar

bottom of page